When using the critical ratio​ (CR) to develop a​ sequence, Part 2 A. a CR of 1.0 means that the job must be scheduled last. B. a CR greater than 1.0 means that the job has some slack. C. a CR less than 1.0 means that the job is ahead of schedule. D. a CR of 1.0 means that the job must be scheduled first.